Cooling Towers Phase I & II



Installation included demolition of six existing cooling towers and reinstall of seven new cooling towers in two phases. Removal of existing foundation and installation of new foundations included site work and grading, new condenser water piping and associated structural pipe bridge with foundation. All new control valves, controls, wiring, and pneumatics were installed. All new electrical service to cooling tower fans, VFD’s, and sump heaters were also installed. Lighting protection and all associated grounding were used. All startup and testing of systems were performed for operational readiness.